CH-08 Premortem (prospective hindsight, inversion) Also serves: Project forward.

Asks a team to assume the plan has already failed and to write the reasons, and produces a grouped list of failure reasons and draft assumptions.

ChallengeEvidence: DocumentedChallenge technique, runs in step 6Strongest statement: describe

What it does

Asks a team to assume the plan has already failed and to write the reasons. Artefact: a ranked or grouped list of failure reasons; read clusters and reasons raised only by sceptical members.

When to use it

Use when a plan is about to be adopted and you want the team to say why it might fail while it can still change.

When it does not fit

It is run after the decision has been taken, or reasons are not converted into plan changes or monitored indicators.

Result format

The result is a ranked or grouped list of reasons the plan failed, written as if the failure had already happened, with the assumptions behind them in an assumptions list. It names the clusters of reasons and the reasons raised only by sceptical members.

Method steps

  1. Read the plan and its goals.
  2. Assume the plan has been carried out and has failed badly.
  3. List every reason that could explain the failure, including the ones people would not normally say.
  4. Go through the list and merge duplicates. Note which reasons the material already points to.
  5. Pick the two or three reasons that would do most harm.
  6. For each, state a change to the plan that would address it.
  7. Write the result: the list of reasons, the top reasons and the changes to the plan.

Steps drawn from: Klein, Performing a project premortem, Harvard Business Review 2007 and CUNY, Principles of management, premortem.

Requirements on the material

PropertyRequirement typeRequirement
Unit of analysisAlways appliesrequires=topic
Appraises source credibilityApplies in some casesno

Not restricted on: Structure, Content type, Variable types, Time structure, How the sample was chosen, Level of detail available, Number of sources, Whether sources can be joined, Amount of material, Known data problems, Producer interest, Source dependence, Origin, Document genre, Language, Personal information, Security classification, Licence.

Minimum materialA plan with a decision date and a team, with about 20 to 30 minutes.
Additional sources needednone
Not for (rules)none
Not for (text)It is run after the decision has been taken, or reasons are not converted into plan changes or monitored indicators.

Choosing and ordering

Kind of techniqueChallenge technique, runs in step 6
Phase tagvalidate
Other phase tagsconclude
Kind of findingrisk; pattern
Question answeredwhat next; why
Strongest statement it supportsdescribe
Needs as input
Makes as output
Must exist firstNone
Loop targetproceed with limit stated

Library checks by stakes

Each stakes level includes the checks of the level below it. Checks that need a person apply at high stakes only, so the process leaves them out at lower stakes (decision 38). Repeatability: judgement dependent.

StakesCheckPerson involvedCounts as a different method
exploratoryassumption and limitation statementnoneno
decision-informingassumption and limitation statementnoneno
decision-informingindependent reviewneeded; left out below high stakesno
high-stakesassumption and limitation statementnoneno
high-stakesindependent reviewneededno
high-stakesexpert reviewneededno
high-stakessecond technique with different assumptionsnoneconditional

Failure modes and limits

Model suitabilityhuman judgement required
Typical model failureProduces a generic failure list from general knowledge in place of the views of the team members, including the sceptics.
Error sourcesinput data; coder or rater judgement; language model
Certainty limitsDescribed by Klein in 2007; the commonly quoted effect figure is unconfirmed and no evidence of improved outcomes was found.

Evidence and tag basis

Documented. Gary Klein described the premortem in Harvard Business Review in 2007: the team assumes the project has failed and generates plausible reasons for the failure. (Klein 2007; CUNY, Principles of management) A 2010 study of 178 university students reported that imagining a plan had failed reduced confidence in it more than pros and cons methods did. (Psychology Today summary of Veinott, Klein and Wiggins 2010)

Tag basis: input profile inference; selection inference; sequencing inference; robustness inference. All tag values are inference unless a source is named.